510 S 3RD ST, Hayti MO 63851-1804 · License #002939306 · Center · Child Care Center
Not published by the state. Owners can add hours via profile claim.
When they operate
Schedule type not published.
Ages served
Ages not published.
5 CSR 25-500.052 · 5 CSR 25-500.052 Annual Requirements (2) (A) states: Evidence of compliance with a fire and safety inspection as conducted by the State Fire Marshal or his/her designee.
The annual fire safety inspection was not approved.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.052 · 5 CSR 25-500.052 Annual Requirements (2) (B) states: Evidence of compliance with local, state, or both, sanitation requirements.
The annual sanitation inspection was not conducted.
Open Not marked corrected in the state record
Open / not marked corrected.
Generated from this facility's specific inspection record
Data synced from Missouri Department of Elementary and Secondary Education, Office of Childhood on Jul 9, 2026 · Source records · Report an error
The facility's outdoor space was not safe for children's activities as evidenced by the white tarp placed under the rubber mulch material is exposed and causing a tripping hazard in the areas under: the see-saw, the swings, both bike spinners, the bus, the slide, the dome climber, and the I/T play area.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (6) (A) 7. states: Areas under and around outdoor equipment shall have continuous maintenance to ensure that the material remains in place and retains its cushioning properties. The resilient material shall be supplemented immediately or replaced as needed.
The fall-zone area under and around outdoor equipment where children might fall and be injured was not covered with impact-absorbing materials to cushion a fall as evidenced by resilient material was not uniformly spread over the fall-zone area.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.102 · 5 CSR 25-500.102 Personnel (3) (A) states: The center director, group child care home provider, all other caregivers, and those volunteers who are counted in staff/child ratios shall obtain at least twelve (12) clock hours of child-care related training during each calendar year. Clock hour training shall be approved by the department.
The requirements for obtaining 12 clock hours each calendar year were not met. For the calendar year of 2024, the staff listed need the following information: Leeqwaisha Moore needs 5.5 hours,.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.052 · 5 CSR 25-500.052 Annual Requirements (1) (C) states: A current list of available equipment.
The equipment list did not contain a list of equipment as required in 5 CSR 25-500.092.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (1) (A) states: The premises shall be safe and suitable for the care of children.
The premises were not safe and suitable as evidenced by there was no working lights in the first hallway bathroom.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (2) (A) 9. states: The facility shall be clean at all times and free of dirt, insects, spiders, rodents or other pests.
There was evidence of dirt/debris in the first hallway bathroom hanging from the vent.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (1) (A) states: The premises shall be safe and suitable for the care of children.
The premises were not safe and suitable as evidenced by the ramp leading outside of the preschool room had toys laying in the walkway causing a tripping hazard.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (2) (A) 6. states: Walls, ceilings and floors shall be finished with material which can be cleaned easily and shall be free of splinters, cracks and chipping paint. Floor covering shall be in good condition. Lead-free paint shall be used for all painted surfaces.
The walls located in the preschool room was/were not in good condition as evidenced by the baseboard along the bottom was not secured exposing holes in sheetrock along the bottom of the wall.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (2) (A) 6. states: Walls, ceilings and floors shall be finished with material which can be cleaned easily and shall be free of splinters, cracks and chipping paint. Floor covering shall be in good condition. Lead-free paint shall be used for all painted surfaces.
The walls located in the school age building was/were not finished with material which can be cleaned easily as evidenced by there was an area by the door with spackling that was not painted.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (2) (A) 9. states: The facility shall be clean at all times and free of dirt, insects, spiders, rodents or other pests.
There was evidence of dirt/debris in the vent in the school age building. The vent was not secured.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (6) (A) 4. states: The play area shall be safe for children's activities, well-maintained, free of hazards such as poisonous plants, broken glass, rocks or other debris and shall have good drainage.
The facility's outdoor space was not safe for children's activities as evidenced by the exposed weed barrier under equipment is a tripping hazard.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (6) (A) 7. states: Areas under and around outdoor equipment shall have continuous maintenance to ensure that the material remains in place and retains its cushioning properties. The resilient material shall be supplemented immediately or replaced as needed.
The fall-zone area under and around outdoor equipment where children might fall and be injured was not covered with impact-absorbing materials to cushion a fall as evidenced by resilient material was not uniformly spread over the fall-zone area.
Open Not marked corrected in the state record
Open / not marked corrected.
5 CSR 25-500.082 · 5 CSR 25-500.082 Physical Requirements of Group Day Care Homes and Day Care Centers (6) (A) 8. states: Concrete, asphalt, carpet, grass or bare soil is not an acceptable surface under outdoor equipment from which children might fall and be injured.
The observed surface area under the slides and teeter-totter on the infant/toddler playground, from which a child might fall consists of grass.
Open Not marked corrected in the state record
Open / not marked corrected.